Central Business Configuration: Add new country


Introduction

In this short blog post we will take a look, how we can add new country to the project scope, if the main scope definition phase was already finished.

Adding new country

Click “Initiate Change” button:

Select 1st option and click “Save” button:

All activities are now reopened to include your additional scope. Open “Define Scope” activity:

Click “Select Countries/Regions”:

Add necessary country:

Now click “Complete Activity“:

You will be reverted to the previous screen. Select here “Manage” for “Request SAP S/4HANA Cloud License-Dependent and Non-Standard Scenarios via Ticket“:

Set “Completed” status for it:

Click “Manage” for “Confirm Scoping is Completed” activity:

Confirm completed milestone:

It will take some time for the activity to be completed: